Briggs & Forrester Special Projects is proud to announce the successful completion of its role as Principal Contractor for the decarbonisation of Nottingham College’s Highfields Campus – an initiative that forms a key part of the College’s broader commitment to sustainability and carbon reduction.
The project was delivered under the Pagabo Mechanical and Electrical Framework and part-funded by the Salix Public Sector Decarbonisation Scheme, reinforcing the shared ambition to reduce carbon emissions across the education sector.
The comprehensive programme included:
- Replacement of gas boiler systems with high-efficiency air source heat pumps (ASHPs).
- Construction of a dedicated external ASHP compound to house new plant.
- Installation of photovoltaic (solar) panels to generate renewable energy on-site.
- Lighting upgrades across three floors to LED standards.
- New incoming main switch panel for improved electrical resilience.
- Drainage improvements to mitigate previous flooding risks.
- New radiators to ensure consistent heating following ASHP installation.
- Integration of all systems into a Building Management System (BMS) for enhanced control and operational efficiency.
- Replacement chiller with associated services installed on the roof area.
- New suspended ceiling installed in three areas on the project.


As part of the refurbishment, Briggs & Forrester installed 1,580 metres of insulated pipework and 310 m² of ductwork, preventing approximately 118,000 kWh of heat loss annually. This equates to:
-
£11,200 annual cost savings for Nottingham College.
-
19.7 tonnes of CO₂e emissions avoided each year. Over a 15-year lifespan, these measures will save an estimated £165,000 and 295 tonnes of carbon, supporting both the College’s and Briggs & Forrester’s Net Zero goals.
Additional environmental measures included:
-
Rooftop solar PV installation to reduce grid dependency.
-
Waste segregation and material reuse on-site.
-
Biodiversity protection and responsible site planning during works.