05 Dec 2024
MEP install progresses on for Briggs & Forrester Living on Brent Cross Town project
Briggs & Forrester Living are progressing well with the MEP installation works on Brent Cross Town Plots 13 and 14 for Client Galliford Try.
Plot 13 is further advanced with all 1st fix M&E works now completed to apartments in all blocks. The installation has now commenced to amenity areas on levels 1, 8 and the ground floor super lobby. 2nd fix M&E works are currently up to level 11 in block A, level 4 in block B & C and level 4 in block D.
Live electrical testing has commenced to all blocks with plots being energised to apartments along with landlord interfacing and services to the basement. Roof works have started with the installation of all smoke extract plant and containment.
Plot 14 mechanical and electrical works have also begun with drainage and rainwater installation to all blocks. The SVP installation is in progress on blocks A, B & C, 1st fix to landlord corridors are completed to level 2 on all blocks and to all apartments.
Two show plots located on level 1 in block A are near completion and works are in motion on the swimming pool, gym and wellness areas including the start of the drainage, ventilation, pipework and electrical installs.