Briggs and Forrester Living are currently undertaking the full MEPH works to Chelsea Creek G&H which is set to be fully completed and handed over early 2024.

We have recently achieved several milestones including completion of all dry risers across all blocks and block H1 wet risers complete up to level 16. Our overall works are at various levels of 1st fix, 2nd fix and testing commissioning with power and water on.

Our main upcoming milestone is to complete all 1st fix installations to block G (G1,G2,G3).

Chelsea Creek is a St George development with blocks G&H comprised of 415 apartments, storage areas, a car park, cycle stores, commercial units and services plant rooms.