07 Jul 2026

Progress Update: 318 Oxford Street Redevelopment

Briggs & Forrester Engineering Services continues to make strong progress on the landmark 318 Oxford Street project in London, working in partnership with McLaren Construction Group to deliver the mechanical, electrical and public health packages.

Construction began in 2025, and the scheme – transforming the former House of Fraser building – is now reaching key delivery milestones.

Key progress highlights include:

  • 🏗️ Cat A installation advancing well
    Substantially complete on Levels 2–5, with Levels 6 & 7 set to reach this stage within the next month
  • 🏢 Reception area taking shape
    High-level reception installation nearing completion
  • ⚙️ Basement works progressing
    Plant areas handed over earlier this year, with MEPH installations now underway
  • ✅ Testing & commissioning underway
    Initial testing activities commenced, including:

    • Cat A distribution boards
    • Condensate pipework testing
    • AHU pressure testing
    • Fire alarm loop testing

The wider refurbishment will deliver over 32,000m² of high-quality commercial space, alongside premium amenities including a gymnasium and winter gardens. A new eighth floor will also feature restaurant facilities.

Built around a heritage-led design, the scheme will introduce striking double-height entrances and a revitalised façade, while targeting BREEAM Excellent, WELL and WiredScore Gold certifications.