Works are progressing well for the Briggs & Forrester Engineering Services team at the 318 Oxford Street project for McLaren Construction Group, with several key milestones recently achieved:

🔧 1st Fix Install is underway across levels 2, 3 & 4 Cat A spaces, with all Cat A floors (Levels 2–7) scheduled to be in progress before the end of 2025

🏛️ In the high-level reception ceiling void, 1st fix installation is also advancing, supporting the transformation of the double-height entrance hall and lobby

🚧 A major project milestone was reached with the successful delivery and positioning of roof equipment. Plant was consolidated off-site in the week prior, with a mobile crane assembled to carry out the lifts

🚿 Riser and WC installations have commenced ahead of programme, marking strong momentum across internal services

🏗️ Another milestone was the delivery and positioning of large equipment in the Sub Basement, enabling leave-down walls and screeding to be completed. This unlocks the next phase: soffit fixings marking the first install elements on the project’s critical path.

The team continues to make excellent progress on this heritage-led transformation in the heart of London’s West End.