Cummins Turbo Technologies
Refurbishment of a manufacturing facility
The brief
Briggs & Forrester were the Management Contractor on the refurbishment of a manufacturing facility for Cummins Turbo Technologies. The project included the refurbishment of mechanical and electrical services including heating, ventilation, lighting, security, electrical supplies and alarms as well as the management of other works including asbestos removal, roof replacement, cladding and sprinkler installation.
The works included a new manufacturing layout, reorganisation of plant and relocation of special products to improve efficiency and reduce costs and was delivered in phased handovers.
Project summary...
Service value
£7.5m
Contract period
41 months
Consultant
Cundalls
Client
Cummins Turbo Technologies
Architect
-
What we did for this project...
We have a fully integrated design and build capability across the group, including 3D coordination and Building Information Modelling. By developing the design and being fully involved in the early stages of a project, we can provide timely design solutions and verification.
The group provides a range of specialist skills encompassing engineering, design, installation, and maintenance. The combined experience, knowledge and expertise of all five divisions enables the group to develop and implement fully-integrated solutions for some of the most complex and demanding mechanical, electrical and public health engineering installations.
We guarantee a smooth handover transition with the project team remaining the main point of contact, the development of commissioning and training plan and regular visits from our team in the months after practical completion.
We offer the design, installation and commissioning of the full range of mechanical and electrical building services, providing turn-key solutions including buildersworks, groundworks, specialist finishes.
Our principal contracting capability has been developed in response to increasing demand from clients with projects requiring highly serviced refurbishment, critical plant replacement, infrastructure and fit-out works.
Related case studies
Industrial
BPUK
London
Project Transit Laundry
Southampton
Intertek
Milton Keynes
BMW Oxford
Oxford
Cummins Turbo Technologies
Huddersfield
Energy From Waste
Gloucester