Kampus

Manchester

New build and refurbished buildings to form a city centre residential development consisting of 537 apartments

Living

Kampus

Living

How can we
help you?

Give us
a call

The brief

The Kampus development in the heart of Manchester city centre comprises the construction of two new 15 storey residential apartment blocks, works to an existing 14 storey block and the refurbishment of two 3 storey Grade II listed buildings. The scheme will provide 537 one and two bed apartments with a dedicated energy centre, management suites and a car park.

Project summary...

Service value

£15.8m

Contract period

26 months

Consultant

Tuv Sud

Client

Mount Anvil

Architect

Chapman Taylor

Added value

Briggs & Forrester utilised pre fabricated bathroom pods which aid programme, reduce waste on site and improve health and safety risks. In addition this allowed for a robust logistics strategy which was required due to the city centre location.

The refurbishment of the Grade II listed buildings provided its own unique set of challenges which meant that early engagement and collaboration with the other key subcontractors and our own supply chain was imperative.

What we did for this project...

We have a fully integrated design and build capability across the group, including 3D coordination and Building Information Modelling. By developing the design and being fully involved in the early stages of a project, we can provide timely design solutions and verification.

The group provides a range of specialist skills encompassing engineering, design, installation, and maintenance. The combined experience, knowledge and expertise of all five divisions enables the group to develop and implement fully-integrated solutions for some of the most complex and demanding mechanical, electrical and public health engineering installations.

We guarantee a smooth handover transition with the project team remaining the main point of contact, the development of commissioning and training plan and regular visits from our team in the months after practical completion.