Spire Healthcare
Nottingham
Briggs & Forrester installed the mechanical, electrical and public health services to the new healthcare facility in Nottingham.
The brief
The new build design and build project consisted of a 3 storey building housing 56-beds, which also included a large outpatient area with 20 consulting rooms, an oncology suite, a six bed critical care unit and a fixed MRI and CT facility. The project achieved a BREEAM Good rating.
Project summary...
Service value
£10.7m
Contract period
55 weeks
Consultant
Parker
Wilson
Client
Spire
Healthcare
Architect
Halliday
Meecham
BFES dealt with all issues in a proactive non-contractual manner and sought to find solutions rather than highlight problems
What we did for this project...
We have a fully integrated design and build capability across the group, including 3D coordination and Building Information Modelling. By developing the design and being fully involved in the early stages of a project, we can provide timely design solutions and verification.
The group provides a range of specialist skills encompassing engineering, design, installation, and maintenance. The combined experience, knowledge and expertise of all five divisions enables the group to develop and implement fully-integrated solutions for some of the most complex and demanding mechanical, electrical and public health engineering installations.
We guarantee a smooth handover transition with the project team remaining the main point of contact, the development of commissioning and training plan and regular visits from our team in the months after practical completion.
Related case studies
Healthcare
Spire Healthcare
Nottingham
HCA Hospital
Birmingham
Whitehouse Medical Centre
Milton Keynes
Atherleigh Park Hospital
Leigh
RJ & AH Hospital
Oswestry
Kettering General Hospital
Kettering
Norwich & Norfolk Hospital
Norwich
Peterborough ICC & MHU
Peterborough
Worcestershire Royal Hospital
Worcestershire